Twenty-day map approval isn't magic — it's a checklist run in the right order. Here it is, with the failure points most owners trip on.
What DHA needs (in submission order)
- Plot ownership document. Allotment letter or transfer letter, with original ownership chain.
- CNIC scan of all registered owners.
- NDC (No Demand Certificate). DHA confirms all dues are clear. This is the most common 5–10 day delay.
- Soil bearing capacity report from a DHA-approved soil testing lab.
- Architectural drawings — site plan, floor plans for each floor, elevations, sections.
- Structural drawings — foundation, column layout, beam and slab reinforcement, bar bending schedule.
- MEP drawings — electrical layout, plumbing layout, sewer connection point.
- Specialist drawings if applicable — basement structural, retaining walls, pool engineering.
- Map fee challan deposited at the DHA-designated bank.
- Architect's stamp and license number on each drawing sheet.
The 20-day timeline, day by day
- Day 1: Submission. File goes to the front desk, intake clerk logs it in.
- Day 2–5: Initial scrutiny. Setback compliance, coverage compliance, FAR check.
- Day 6–10: Structural and MEP scrutiny by engineering desk.
- Day 11–14: Site visit by DHA inspector to verify plot pegs and existing boundary.
- Day 15–18: Final review, any minor objections returned for clarification.
- Day 19–20: Approval stamp and file collection.
The three failure points
- Setback violation on the drawing. 60% of returned files have a small setback error — a 0.5ft cantilever or a porch encroaching by 1ft. The map gets bounced back, you fix the drawing, you re-submit, and the cycle restarts. Always have the setbacks drawn dimensioned explicitly.
- NDC not actually clear. Owners assume their NDC is fine, but a small unpaid development fee from years back triggers a hold. Pull a fresh NDC before submission — it's worth the PKR 5,000 to confirm.
- Soil report from a non-approved lab. DHA maintains a list of approved soil testing labs. A report from any other lab is rejected immediately. We use Lahore Engineering Services, MEC, or NESPAK.
What we do
Our compliance desk runs a pre-submission audit on every drawing before it leaves our office. Setbacks, coverage, FAR, MEP coordination — all verified by an internal team that doesn't draw the building, only checks it. Catches 95% of objections before they happen, which is why our average approval timeline is 18–22 working days.